Joe Tadlock

Joe Tadlock

Roseville, California, United States
2K followers 500+ connections

About

Executive Management Experience: The professional positions held over the past…

Articles by Joe

See all articles

Contributions

Activity

Join now to see all activity

Experience

  • Allerion Consulting Group, Inc. Graphic

    Allerion Consulting Group, Inc.

    Roseville, California, United States

  • -

    Roseville, California

  • -

    Sacramento

  • -

    Sacramento, California Area

  • -

    Auburn, California

  • -

  • -

    Sacramento, California Area

Volunteer Experience

  • Board Member

    Junior Livestock Association - Auburn Gold Country Fairgrounds

    - 2 years 7 months

    Children

    Provide volunteer support for the fairgrounds relating to 4H and Future Farmers of America (FFA).

  • Quality Control Manual Review Member

    Construction Managers Association of America

    Education

    Provided technical support related to the development of quality control procedures manual for the association training and certification process.

  • Volunteer

    The Gathering Inn

    - 2 years 3 months

    Poverty Alleviation

    Today, The Gathering Inn provides a community-based response to people in need in south Placer County by offering hope, dignity and a secure place to rest at night, in addition to a wide range of services that help clients get back on their feet again.

  • Member

    Auburn Gold Country Rotary Club

    - 6 years 1 month

    Social Services

Courses

  • Accounting

    -

  • Business Analytic Mathmatics

    -

  • Macro Economic

    -

  • Managerial Accounting

    -

  • Micro Economics

    -

Projects

  • FOLSOM DAM MODIFICATIONS, PHASE IV CONSTRUCTION

    Served as the Project Manager for inspections and materials testing services as a sub to Kiewit Infrastructure. The fourth phase will construct the new spillway’s 1,100-foot-long approach channel on the reservoir side of the control structure, essentially a second dam that’s currently under construction, and the 3,027-foot-long spillway chute and stilling basin on the downstream side. The stilling basin works as an energy dissipater to slow the water as it enters the American River. Project…

    Served as the Project Manager for inspections and materials testing services as a sub to Kiewit Infrastructure. The fourth phase will construct the new spillway’s 1,100-foot-long approach channel on the reservoir side of the control structure, essentially a second dam that’s currently under construction, and the 3,027-foot-long spillway chute and stilling basin on the downstream side. The stilling basin works as an energy dissipater to slow the water as it enters the American River. Project features include Approach Channel, Approach Walls, Slab and rock trap, Upper Chute, Stepped Chute, Stilling Basin, Dike 7 Stockpile of existing material for Ph IV use, Dike 8 Optional Ph IV material spoil area, Mormon Island Auxiliary Dam (MIAD) staging and spoil area.

    Other creators
    See project
  • MORMON ISLAND AUXILIARY DAM (MIAD), FOLSOM, CALIFORNIA

    Served as the Project Manager for the setting up the on-site lab and staffing both field technicians and lab technicians for Suulutaaq (GC). This project was under the United States Department of the Interior, Bureau of Reclamation to upgrade the Mormon Island Auxiliary Dam (MIAD). MIAD is the second phase of “Safety of Dams” modifications to the Mormon Island Auxiliary Dam. Located approximately two miles east of Folsom, California, MIAD is a component of the “Folsom Project,” which also…

    Served as the Project Manager for the setting up the on-site lab and staffing both field technicians and lab technicians for Suulutaaq (GC). This project was under the United States Department of the Interior, Bureau of Reclamation to upgrade the Mormon Island Auxiliary Dam (MIAD). MIAD is the second phase of “Safety of Dams” modifications to the Mormon Island Auxiliary Dam. Located approximately two miles east of Folsom, California, MIAD is a component of the “Folsom Project,” which also includes Folsom Dam and Reservoir and eight earthfilled dikes. The construction means and methods for the MIAD project include the overlay of five distinct material zones with ten different zone configurations to be placed on the downstream side of the dam. These zoned materials, consisting of sand, gravel, and crushed rock, will be processed onsite to meet the Bureau of Reclamation’s stringent specifications. I suppported the Quality Control Plan to address: 1) the distinct zone separation requirements for proper moisture content, 2) coordination between adjacent zones due to lift thickness and 3) prevention of contamination from adjacent zones.

    The top of the dam, currently stands at 100 feet above Green Valley Road and is 900-feet long by 25 feet wide. When complete, the dam reinforcement will have include an estimated 1.7 million cubic yards and widening the crest of the dam an estimated 80 feet. This project consists of site preparation to include construction for development of contractor use areas; implementation of security measures; clearing and grubbing; development of water control and erosion measures; and excavation of 106,000 cubic yards of existing embankments. The work also consists of processing, sorting, stockpiling, and placing 450,000 cubic yards of filter and gravel drain material; 1.3 million cubic yards of shell-fill material from an existing waste/stockpile located on-site, and 51,000 cubic yards of rip rap and coble slope protection.

    Other creators
    See project
  • California Department of Corrections (On-Call Code Compliance Contract) Northern California

    Project Director managing the OSHPD, General Inspection, Special Inspection and Materials Testing services for the Northern California region. Contract management included coordination with CDCR Inspection Division Management, recruiting Code Compliance Inspectors (OSHPD & Project Inspectors), ensuring staffing needs were met for special inspectors, materials testing and support services like cathodic protection. The program encompasses the following requirements:

    THE FUTURE OF…

    Project Director managing the OSHPD, General Inspection, Special Inspection and Materials Testing services for the Northern California region. Contract management included coordination with CDCR Inspection Division Management, recruiting Code Compliance Inspectors (OSHPD & Project Inspectors), ensuring staffing needs were met for special inspectors, materials testing and support services like cathodic protection. The program encompasses the following requirements:

    THE FUTURE OF CALIFORNIA CORRECTIONS BLUEPRINT
    In 2014, the California Department of Corrections and Rehabilitation (CDCR) continued implementation of facility improvements contained in its “Blueprint”. This comprehensive plan was designed to improve the prison system, end federal court oversight, and save billions of dollars. SB 1022 also authorized construction of three Level II dorm infill projects at existing prisons to meet the increased need for Level II housing.

    HEALTH CARE FACILITY IMPROVEMENT PROGRAM
    CDCR initiated HCFIP projects at adult institutions. These projects will improve the physical plant infrastructure to complement the medical classification system and improve the provision of outpatient medical care to the inmate population. Construction phase activities commenced at seven prisons during 2014. All planned improvements are expected to be completed in fiscal year (FY) 2017-18. The planned improvements primarily focus on providing exam rooms and other clinical spaces with appropriate confidentiality as prescribed by the federal Health Insurance Portability and Accountability Act, adequate infection control systems, as well as medication distribution facilities.

    Other creators
    See project
  • VETERANS ADMINISTRATION – MATHER HOSPITAL, SACRAMENTO, CALIFORNIA

    Served as Project Manager on six different projects for the upgrade and expansion of the hospital. These projects were managed by the Department of Veterans Affairs for over a five (5) year period, in Sacramento, including the construction of infrastructure upgrades, two new buildings, emergency room reconstruction, a new parking structure and numerous remodels throughout the main hospital. This facility has been transformed from the ‘former’ Mather Air Force Base in Sacramento, California.…

    Served as Project Manager on six different projects for the upgrade and expansion of the hospital. These projects were managed by the Department of Veterans Affairs for over a five (5) year period, in Sacramento, including the construction of infrastructure upgrades, two new buildings, emergency room reconstruction, a new parking structure and numerous remodels throughout the main hospital. This facility has been transformed from the ‘former’ Mather Air Force Base in Sacramento, California. My team provided site Geotechnical services including foundation inspection and certification, and soil and asphalt compaction testing and inspection. Field Staff performed Special Inspection and engineering support services for the project including re-enforced concrete and masonry, field welding, Non-destructive Examination of Welds (NDE), and fireproofing inspection. Additional support services included providing all laboratory testing and engineering review of concrete, mortar, grout, masonry prisms, bolt, fireproofing, and soils.

    Other creators
    See project
  • C-5 Runway 21L-03 & SLZ Runways, Travis AFB

    Managed the contract to provide a USACE QC Manager, Field Technicians and Laboratory Services for almost 4 years. It is the intent of this solicitation to contract for all labor, material and equipment to maintain and repair airfield pavements at the Travis Air Force Base, Fairfield, CA. This is an Indefinite Quantity Type Contract with a base year and four one year options. The maximum ordering capacity will be $8,000,000 for the base year and $5,000,000 for each option year. The work requires…

    Managed the contract to provide a USACE QC Manager, Field Technicians and Laboratory Services for almost 4 years. It is the intent of this solicitation to contract for all labor, material and equipment to maintain and repair airfield pavements at the Travis Air Force Base, Fairfield, CA. This is an Indefinite Quantity Type Contract with a base year and four one year options. The maximum ordering capacity will be $8,000,000 for the base year and $5,000,000 for each option year. The work requires primarily full depth PCC slab replacement and including but not be limited to demolition, excavation and disposal of existing Portland cement concrete (PCC) and asphalt concrete (AC) pavements, bases, sub-bases, sub-grades, cement treated bases, lime treated bases, and similar in accordance with environmental regulations. The work also includes preparation and compaction of existing bases, sub-bases, and sub-grades to remain; replace unsatisfactory bases, sub-bases, and sub-grades with satisfactory materials, provide full and partial depth repairs for PCC slabs; provide full depth repairs for AC pavements; repair joints and cracks; provide prime and tack coat; provide pavement reinforcing fabric; provide AC pavement overlay; provide AC surface treatments; replace damaged and/or adjust existing catch basins, manholes, and similar; provide airfield pavement markings; provide airfield lighting system, fixtures, cans and other required components; provide closed markers and traffic barriers for runways, taxiways, aprons and other airfield pavement; provide airfield pavement rubber removal; and dispose of all construction materials off the base property in an approved landfill.

  • HAMILTON WETLANDS RESTORATION PROJECT SITE, NOVATO, CALIFORNIA

    Served as the Project Manager for Quality Control Services including field technicians and laboratory testing services. The work described consists of all tasks to complete the Wetland Restoration Project (HWRP) located in Novato, California and represents the culmination of over ten years of effort. Included is final shaping of the South Seasonal Wetlands and Tidal Panne Area, and deconstruction of temporary earthen structures, and the dredging of a channel in the Tidal Wetland Area. Also…

    Served as the Project Manager for Quality Control Services including field technicians and laboratory testing services. The work described consists of all tasks to complete the Wetland Restoration Project (HWRP) located in Novato, California and represents the culmination of over ten years of effort. Included is final shaping of the South Seasonal Wetlands and Tidal Panne Area, and deconstruction of temporary earthen structures, and the dredging of a channel in the Tidal Wetland Area. Also included in the contract are three optional components: one to construct the Bay Trail along the site, the second to dredge the pilot channel from the bay to the project, and the third option to breach and degrade the bay front levee and to remove remaining access infrastructure.

    Seasonal Wetlands Shaping Component:
    This component consists of upland earthwork to shape and complete the south seasonal wetlands (SSW) and Tidal Panne areas. The total work (roughly 300,000 CY) includes both excavation and placement of previously dredged material within approximately 75 acre (SSW) and 10 acre (Tidal Panne) work areas (all cut and fills are internal to the areas of construction).

    Tidal Wetland Component:
    This is a multi-tasked component that prepares the Tidal Area of the site for Breach. It includes deconstruction of 2 pump-house facilities, and the removal of a 30" pipe and its bedding that was previously used in bringing the dredged material to the site. Also included is the removal of temporary earthen connector berms which had separated the overall Tidal Area into separate cells during previous filling operations (approximately 45,000 cu yds of excavation), and the digging out of the channel near the breach internal to the site (approximately 50,000 cu yds of excavation).

    See project
  • MORRISON CREEK AT UNION PACIFIC RAILROAD - CONTRACT 2A

    Served as the Project Manager for Materials Testing Services for both field and in the lab. The Morrison Creek Floodwall between the confluence of Union house Creek and the Union Pacific Railroad (UPRR) bridge consists of a 2,850 linear feet of reinforced concrete flood wall and 80 linear feet of levee along the east side of the UPRR right-of-way (ROW) the total length of UPRR right-of-way impacted by the project is 3,168 linear feet (0.6 miles) from Milepost 130.43 to Milepost 131.03. The…

    Served as the Project Manager for Materials Testing Services for both field and in the lab. The Morrison Creek Floodwall between the confluence of Union house Creek and the Union Pacific Railroad (UPRR) bridge consists of a 2,850 linear feet of reinforced concrete flood wall and 80 linear feet of levee along the east side of the UPRR right-of-way (ROW) the total length of UPRR right-of-way impacted by the project is 3,168 linear feet (0.6 miles) from Milepost 130.43 to Milepost 131.03. The reinforced concrete floodwall will be built to an elevation of 20.5 feet with an approximate height from 0 to 18 feet above existing grade. At the south end of the alignment the floodwall transitions to an earthen levee section where an existing SMUD 20" Gas Pipeline crosses the existing Union house Creek levee (1B2) alignment. The levee is approximately 80-feet long with a 2:1 landside slope, 3:1 waterside slope and a 12-foot crest width. A 12-foot wide aggregate base patrol road with a pre-cast concrete drainage system runs along the entire alignment along the waterside of the floodwall.

    Other creators
    See project
  • ANTLERS BRIDGE REPLACEMENT PROJECT, DISTRICT 2, REDDING, CALIFORIA

    - Present

    REDDING – The California Department of Transportation along with the Federal Highway Administration has awarded a contract for the Antlers Bridge Replacement Project to Tutor Perini of Sylmar, CA for $125 Million, 43% below the engineer’s estimate. After final contract approval scheduled for the beginning of October, construction will begin in mid-October. The project is financed with federal and state transportation dollars through the State Highway Operation and Protection…

    REDDING – The California Department of Transportation along with the Federal Highway Administration has awarded a contract for the Antlers Bridge Replacement Project to Tutor Perini of Sylmar, CA for $125 Million, 43% below the engineer’s estimate. After final contract approval scheduled for the beginning of October, construction will begin in mid-October. The project is financed with federal and state transportation dollars through the State Highway Operation and Protection Program.

    This project will replace Antlers Bridge on Interstate 5 in Shasta County over the Sacramento River arm of Shasta Lake near the community of Lakehead. The new structure will be a 1,942-foot long, 104-foot wide, five-span concrete bridge. It will be constructed on a new parallel alignment slightly east of the existing bridge. In addition, a 0.4 mile long section of highway south of the bridge will be realigned and the existing 1,330-foot long structure will be demolished and removed.

    See project
  • REPAIR & REPLACE SEGMENTS AT 300 &600 RAMPS, TRAVIS AFB

    REPAIR & REPLACE RAMP 300 & 600 PROJECTS, TRAVIS AIR FORCE BASE, CA. These were typically contractor sole source contracts from 2004 to 2011. Purpose of the contracts were to add an additional concrete section of the pull-through area and spots related to RAMP 300 & 600 adjacent to the runway. The work was to add an additional concrete section of the ramps and pull-through area, 50' wide by a length reaching to Taxiway Lima and to provide needed spall repair at edges of existing concrete and/or…

    REPAIR & REPLACE RAMP 300 & 600 PROJECTS, TRAVIS AIR FORCE BASE, CA. These were typically contractor sole source contracts from 2004 to 2011. Purpose of the contracts were to add an additional concrete section of the pull-through area and spots related to RAMP 300 & 600 adjacent to the runway. The work was to add an additional concrete section of the ramps and pull-through area, 50' wide by a length reaching to Taxiway Lima and to provide needed spall repair at edges of existing concrete and/or asphalt.

    These segments required quality control staffing of 2-4 on-site staff members for replacement of the numerous RAMP segments. Quality Control staff had extensive concrete related experience and working in a high production environments. Quality Control staff each possessed over 5 to 10 years of concrete related experience and working in a high production environment.

    Other creators
  • Northridge Hospital Medical Center (Facility No. 11906)

    Responsible for being the Project Manager for the seismic investigation of the hospital to address seismic design requirements. The existing F-Tower buildings, Main Tower (Building 8A) and Elevator Tower (Building 8B), are located on the north side of the campus adjacent to Roscoe Boulevard. The towers were constructed circa 1966 under the 1963 Uniform Building Code. In 1970, the Original Lab Building (Building 7A) was constructed over the F-Tower basement under the 1968 Uniform Building Code…

    Responsible for being the Project Manager for the seismic investigation of the hospital to address seismic design requirements. The existing F-Tower buildings, Main Tower (Building 8A) and Elevator Tower (Building 8B), are located on the north side of the campus adjacent to Roscoe Boulevard. The towers were constructed circa 1966 under the 1963 Uniform Building Code. In 1970, the Original Lab Building (Building 7A) was constructed over the F-Tower basement under the 1968 Uniform Building Code. The buildings were not OSA reviewed. The F-Tower Main Tower is a 90 foot by 130 feet, five-story clay masonry shear wall structure over a concrete basement.

    Services:
    Documentation of field conditions
    Reinforcing Steel Locations
    Rebar Layout Diagrams (Size & Orientation)
    Concrete Core Testing (Modules of Elasticity, Compression, Unit Weight)
    Metal Deck Coupons (Yield Strength, Ultimate Strength & Modules of Elasticity)
    Steel Coupons (Yield Strength, Ultimate Strength & Modules of Elasticity)
    Weld Testing (Chemical Analysis & Weld Hardness – Bernell)

    Challenges & Solutions:
    Seismic investigations require an experienced team to understand unforeseen conditions and implements problem solving solutions to achieve program objectives. Wall thicknesses, access challenges and knowledge based experience ensured schedules and cost impact issues were mitigated in real time. Unforeseen conditions required a team who adapted to deviations from as-built drawings and provide guidance when information was vague or unattainable.

    Our staff developed unique steel NDT and Destructive Testing procedures for structural steel components and concrete cores including customized testing documenting procedures. This proactive approached resulted in additional data analysis beyond the contract document requirements. Our team continuously looked at ways to enhance the quality and depth of data needed to comply with SB 1953 regulations.

    Other creators
  • The Warehouse Artist Lofts (formerly known as Capitol Lofts), Sacramento

    -

    The Warehouse Artist Lofts or the WAL (formally the Capitol Lofts) is the proposed rehabilitation of the existing six story historic CADA warehouse building, into a residential mixed-use apartment complex. Located in the heart of the R Street Historic District between 11th and 12th Streets, this exciting project includes new residential housing construction east of the historic warehouse building, a below grade parking garage, and ground floor retail along R Street. The 116 housing units and…

    The Warehouse Artist Lofts or the WAL (formally the Capitol Lofts) is the proposed rehabilitation of the existing six story historic CADA warehouse building, into a residential mixed-use apartment complex. Located in the heart of the R Street Historic District between 11th and 12th Streets, this exciting project includes new residential housing construction east of the historic warehouse building, a below grade parking garage, and ground floor retail along R Street. The 116 housing units and 13,000 square feet of commercial spaces will be marketed to the Sacramento artist community with the goal to make the R Street Historic District also an art and culture district. The WAL is being undertaken jointly by the Capitol Lofts-Sacramento, LLC (a partnership of CFY Development and Holliday Development) and the Capitol Area Development Authority (CADA).

    Other creators
    See project
  • FREEPORT REGIONAL WATER AUTHORITY SACRAMENTO RIVER – WATER INTAKE FACILITY

    -

    Provided Contract Management for Special Inspection Services. The new $121 million Water Intake Facility and pumping plant located on the Sacramento River, upstream of the town of Freeport, will divert water and pump it through pipelines to other FRWP facilities. Eight vertical turbine pumps with 2,000 horsepower electric induction motors will have the capacity to pump up to 185 mgd of water per day. Components of the facility include an in-river intake fish screen, sheet-piled in-river…

    Provided Contract Management for Special Inspection Services. The new $121 million Water Intake Facility and pumping plant located on the Sacramento River, upstream of the town of Freeport, will divert water and pump it through pipelines to other FRWP facilities. Eight vertical turbine pumps with 2,000 horsepower electric induction motors will have the capacity to pump up to 185 mgd of water per day. Components of the facility include an in-river intake fish screen, sheet-piled in-river transition structure, electrical substation, surge control facility, sediment collection and settling basin system, and utilities. FRWA has constructed a slurry wall on the levee in order to strengthen the levee near the South Pocket neighborhood, in advance of scheduled levee improvements by the U.S. Army Corps of Engineers. A landscaped buffer is being maintained between homes adjacent to the facility property and the structures. FRWA has commissioned a regional artist to construct an art and poetry wall on the front of the structure. The facility includes state-of-the-art fish screens, valves, VFDs and large diameter pipeline (72-inch and 84-inch). In addition, two micro-tunnels were bored under I-5 and Freeport Boulevard.

    See project
  • SUTTER BYPASS - EAST BORROW CANAL SACRAMENTO RIVER – WEIR NO. 2 PROJECT

    -

    Serviced as the Project Manager for Materials Testers and Laboratory Testing Services. A new weir structure and fish ladder will be constructed to facilitate passage of adult and juvenile salmon and steelhead past the structure over a greater range of flows. FPIP staff prepared a preliminary engineering technical report (18 MB) in 2003 and a mitigated negative declaration and initial study for the project in 2008.

    The Sutter Bypass East Borrow Canal Water Control Structures Project…

    Serviced as the Project Manager for Materials Testers and Laboratory Testing Services. A new weir structure and fish ladder will be constructed to facilitate passage of adult and juvenile salmon and steelhead past the structure over a greater range of flows. FPIP staff prepared a preliminary engineering technical report (18 MB) in 2003 and a mitigated negative declaration and initial study for the project in 2008.

    The Sutter Bypass East Borrow Canal Water Control Structures Project proposes to remove the existing weir and fish ladder and replace them with new structures that are more effective and safer to operate. Approximately 100 ft downstream of the existing weir, DWR will construct a new weir that has the same dimensions as the existing weir, and a new fish ladder on the bank opposite the existing fish ladder. The new weir will have three main channels, which utilize remotely operated inflatable Obermeyer gates to control water levels upstream in the EBC, and six side bays controlled by manually removable flashboards.

    See project

Honors & Awards

  • Labor Compliance Presenter Appreciation

    American Contract Compliance Association

  • Certificate of Appreciation

    City of Auburn

    Worked with City Council and City Manager on a marketing proposal resulting in attracting the State of California, Sierra Nevada Conservancy establishing their headquarters in Auburn, California.

  • Rotary - Rising Star (2006)

    Auburn Gold Country Rotary

  • Business Consultant of the Year

    Junior Achievement

Languages

  • English

    Native or bilingual proficiency

  • Japanese

    Limited working proficiency

Recommendations received

More activity by Joe

View Joe’s full profile

  • See who you know in common
  • Get introduced
  • Contact Joe directly
Join to view full profile

Other similar profiles

Explore collaborative articles

We’re unlocking community knowledge in a new way. Experts add insights directly into each article, started with the help of AI.

Explore More

Others named Joe Tadlock in United States

Add new skills with these courses